The schedule for the planned shutdown of hot water supply in Vitebsk for 2024 has been published
The purpose of the upcoming work is to prepare for the autumn-winter period of 2024-2025. In this regard, a planned shutdown of hot water supply will begin in Vitebsk.
Phased schedule for hot water shutdown in Vitebsk
|
Mini-CHP plant "Vostochnaya" |
from May 15 to May 27 |
|
Boiler house "Yuzhnaya", Stage I |
from June 3 to June 15 |
|
Vitebsk CHP plant |
from July 23 to August 4 |
|
Boiler house "Yuzhnaya", Stage II |
from August 12 to August 24 |
|
Boiler house "Severnaya" |
from August 19 to August 31 |
From May 15 to May 27 – Mini-CHP plant "Vostochnaya"
From 9:00 on 15.05.2024 to 23:59 on 27.05.2024, scheduled repair of heating networks from the mini-CHP plant "Vostochnaya" will be carried out. In this regard, there will be no hot water supply in residential buildings and other facilities located at the following addresses:
- Suvorova St.;
- Kupaly St.;
- Krylova St.;
- Mayakovsky St.;
- Politekhnicheskaya St.;
- Sovetskaya St.;
- Bauman St.;
- Lenina St., 36, 40, 44/2, 46/1, 48, 50/6, 52/13, 52, 52a, 52b, 53, 54, 55, 55a, 56, 57, 58, 59/11, 60, 61, 62/19, 63, 64, 65, 66, 65a, 67/21, 68, 69, 70, 71, 72, 73/2, 74, 75, 76;
- Tolstogo St., 1, 3, 5;
- Kotovskogo St., 15, 17, 21, 23;
- 5th Frunze St., 2, 6, 14;
- 2nd Frunze St., 4;
- all properties on Pravdy St. (except for buildings No. 13/7, 14/5, 18, and 24);
- Lyudnikova Ave., 11, 11a, 12, 13, 14, 15, 16, 17;
- Moskovsky Ave., 66/1, 68, 70, all properties of the Technological University, 74 bldg. 1, 74 bldg. 2, 74 bldg. 3, 74 bldg. 4, 74 bldg. 5, 74 bldg. 6; 74a, 76, 78, 80, 82, 84, 80a (Kindergarten No. 89), 106;
- Frunze Ave. (except for 11, 13a, 13, 13a/1);
- Smolenskaya St. (except for railway buildings No. 4 bldg. 1, 4 bldg. 2, 4 bldg. 3, 4 bldg. 4, 4 bldg. 5, 4 bldg. 6);
- all properties on Tereshkova St., Krasnoflotskaya St., Poperechnaya St., Lugovaya St., Beresten St., Lazo St., Narodnaya St., Mira St., Chapayeva St., June 26th St., Dovatora St., Uritskogo St., Deputatskaya St., Putna St., Kommunisticheskaya St., Chekhova St., Kutuzova St., Kuybyshev Ave., Griboyedov St., Gorovtsa St.;
- 2nd Sadovaya St., 6, 8, 10/3, 9, 11, 13, 13a, 15;
- 3rd Sadovaya St., 10;
- 6th Klinicheskaya St., 44;
- Klinichesky Lane, 3, 5;
- Aviatsionny Lane, 2;
- industrial properties on S. Pankova Passage;
- Tulovo settlement, Tsentralnaya St., Novosyolov St., Molodezhnaya St., Yubileynaya St., Sadovy Lane;
- "Cheryomushki" microdistrict;
- "Bilevo" microdistrict.
Hydraulic tests of heating networks at increased pressure will be carried out from 9:00 AM on 17.05.2024 until 11:59 PM on 18.05.2024.
From June 3 to June 15 – "Yuzhnaya" boiler house, stage 1
Repair of heating networks from the "Yuzhnaya" boiler house (stage 1) will be carried out from 9:00 AM on 03.06.2024 until 11:59 PM on 15.06.2024. In connection with this, hot water supply will be unavailable at the following properties:
- Moskovsky Ave., 29;
- all properties on V. Internatsionalistov St.;
- all properties on Meditsinskaya St.;
- Gen. Margelov St., 1;
- Stroiteley Ave., 1; 1a; 2; 3 bldg. 1, 3 bldg. 2, 3 bldg. 3; 3b; 5 bldg. 1, 5 bldg.2; 5a (Kindergarten No. 106); 6; 7; 7 bldg. 1, 7 bldg. 2, 7 bldg. 3; 8; 8 bldg. 2; 11; 11a; 15; 23 ("Ledovy Dvorets");
- VSMU Clinic;
- Luchosa Hotel;
- P. Brovki St., 15; 15 bldg. 1, 15 bldg. 2, 15 bldg. 3, 15 bldg. 4, 15 bldg. 6; 17 bldg. 1, 17 bldg. 2, 17 bldg. 3, 17 bldg. 4; 19 bldg. 1, 19 bldg. 2, 19 bldg. 3, 19 bldg. 4; 21 bldg. 1, 21 bldg. 2, 21 bldg. 3; 23 bldg. 1, 23 bldg. 2; 25; 39; 37;
- Oncology dispensary facilities, nephrology building, regional hospital, children's home, maternity hospital No. 2, District Sanitary and Epidemiological Station;
- Pobedy Ave., 15 bldg. 1, 15 bldg. 4; 17; 17a; 19; 19a (Kindergarten No. 100); 21; 21 bldg. 1, 21 bldg. 2, 21 bldg. 3, 21 bldg. 4, 21 bldg. 5; 23; 23a (Kindergarten No. 102); 23d; 25 bldg. 2, 25 bldg. 3; 25a (Kindergarten No. 103); 27; 27 bldg. 1, 27 bldg. 2; 29; 29 bldg. 2, 29 bldg. 3, 29 bldg. 4, 29 bldg. 5; 29a (Sports School No. 39); 31; 31 bldg. 1, 31 bldg. 2; 33; 35; 37; 37 bldg. 1; 41; 41 bldg. 1; 43; 43 bldg. 1; 45; 45 bldg. 1; 47; 49; 53; 55; 55 bldg. 1, 55 bldg. 2, 55 bldg. 3, 55 bldg. 4; 57; 57 bldg. 1; 59; 59 bldg. 1, 59 bldg. 2, 59 bldg. 3; 61; 61 bldg. 1, 61 bldg. 2;
- Chkalov St., 11 bldg. 10, 11 bldg. 11, 11 bldg. 12, 11 bldg. 13; 12; 21; 21 bldg. 1, 21 bldg. 2; 23, 23 bldg. 1, 23 bldg. 2, 23 bldg. 2a (Kindergarten No. 14); 25; 25g; 25a (Kindergarten No. 12); 25 bldg. 1, 25 bldg. 1a, 25 bldg. 2, 25 bldg. 2a, 25 bldg. 3, 25 bldg. 4, 25 bldg. 5, 25 bldg. 6, 25 bldg. 6a, 25 bldg. 7; 27 bldg. 1, 27 bldg. 3; 27; 27b (Kindergarten No. 15); 28 bldg. 1, 28 bldg. 2, 28 bldg. 3, 28 bldg. 4 (Kindergarten No. 97), 28 bldg. 5; 29; 29 bldg. 1, 29 bldg. 2; 30; 30 bldg. 1, 30 bldg. 2, 30 bldg. 3, 30 bldg. 4, 30 bldg. 5; 31; 32; 32 bldg. 1, 32 bldg. 2, 32 bldg. 2a, 32 bldg. 3, 32 bldg. 4, 32 bldg. 5, 32 bldg. 6, 32 bldg. 7 (Gymnasium No. 8); 34; 36; 36 bldg. 1, 36 bldg. 2, 36 bldg. 3; 36a (Kindergarten No. 101); 37 bldg. 1, 37 bldg. 2, 37 bldg. 3; 38; 38 bldg. 1, 38 bldg. 2; 39; 39 bldg. 1, 39 bldg. 2, 39 bldg. 3; 40; 41; 41 bldg. 1, 41 bldg. 2, 41 bldg. 3, 41 bldg. 4; 44; 43 bldg. 1, 43 bldg. 2, 43 bldg. 3, 43 bldg. 4; 43a; 44 bldg. 1; 47; 47 bldg. 1, 47 bldg. 2; 47a (Secondary School No. 45); 48; 49 bldg. 1, 49 bldg. 2, 49 bldg. 3; 50a; 50 bldg. 1, 50 bldg. 2, 50 bldg. 4; 51; 51 bldg. 2; 52; 52 bldg. 1, 52 bldg. 2, 52 bldg. 3; 54 bldg. 1; 56; 56 bldg. 4; 60; 60 bldg. 1; 62; 62 bldg. 1; 64; 64 bldg. 1; 64a (Kindergarten No. 112); 66; 66 bldg. 1;
- Chernyakhovsky St., 14 bldg. 5 (Secondary School No. 33); 23; 25; 25a (Vetrats Hotel); 27; 27a; 27 bldg. 1; 29; 31 bldg. 5; 32; 31 bldg. 2 block: A, B, C, D; 32 bldg. 1, 32 bldg. 2, 32 bldg. 3; 33; 34a; 34/13; 34; 34v; 34 bldg. 1; 34 bldg. 2, 34 bldg. 3, 34 bldg. 4; 35 bldg. 1; 36; 36 bldg. 1, 36 bldg. 2; 38; 42; 44.
From 9:00 on 03.06.2024 to 23:59 on 04.06.2024, hydraulic tests of heating networks at elevated pressure will be carried out.
From July 23 to August 04 – Vitebsk CHP Plant
From 9:00 on 23.07.2024 to 23:59 on 04.08.2024, scheduled maintenance of heating networks from Vitebsk CHP Plant will be performed. In this regard, hot water supply will be unavailable at the following facilities:
all facilities in the area of 39th Army Street, Pavlov Street, Belinsky Street, Bobel Street, Beloborodov Street, Budyonny Street, Bumagin Street, Byadulya Street, B. Khmelnytsky Street, 2, 3, 4/16, 5/14 ("Belsoyuzpechat"), 7/13, 10 (Justice Department, employment center), Vostretsov Street, Vitebskaya Street, Voykov Street, Herzen Street, Gorodokskaya Street, Gorbachevsky Street, M. Gorky Street, Goncharnaya Street, Gogol Street, Glinka Street, Grazhdanskaya Street, Dobrolyubov Street, Dimitrov Street, Evstigneev Street, Jaures Street, Zamkovaya Street, Zenkova Street, Zolnogorskaya Street, Kalinin Street, Kosmonavtov Street, Kirov Street, Koltsov Street, Komsomolskaya Street, 5th Kooperativnaya Street, Krasin Street, Kondratyev Street, Lomonosov Street, Lokomotivnaya Street, Leonov Street, K. Marx Street, Michurin Street, Myasnikov Street, Naberezhnaya Street, Novy Byt Street, Nekrasov Street, Oktyabrskaya Street, Ordzhonikidze Street, Porokhovaya Street, Pokrovskaya Street, Pushkin Street, Proletarskikh Street, Pryadilnaya Street, Repin Street, Revolyutsionnaya Street, Rozy Lyuksemburg Street, Sotsialisticheskikh Street, Smetanin Street, Sovetskoy Armii Street, Sverdlov Street, per. Stakhanovsky, per. Stroitelny, Ilyinsky Street, 4th Industrialnaya Street, Shagal Street, Shirokaya Street, Engels Street, per. Energetikov, ul. 4th Chkalova, Yamskaya Street, pl. Pobedy, pl. Svobody;
- Lenina Street, 6, 8, 8a, 10, 12, 14, 16, 16/22, 16/7, 17, 18, 19, 20, 23, 24, 26/2, 26a, 28, 30/21, 32, 33a, 35,
- Leningradskaya Street, 2, 4, 15, 16, 17, 18, 27, 37, 39;
- Pravdy Street, 3, 5, 7a, 8a, 18, 18 k.1, 24;
- Titova Street, 12, 12a, 14, 16, 20, 20a, 20 k.1, 20 k.1a, 22, 24;
- Chernyakhovsky Avenue, 5, 7, 9, 11, 13, 13a, 14, 14a, 15, 16, 17, 17a, 18, 19, 20, 20 k.3, 22;
- Frunze Avenue, 11, 13a, 13, 13a/1;
- Kirovsky settlement.
Hydraulic testing of heating networks at elevated pressure will be carried out from 9:00 on 23.07.2024 to 23:59 on 25.07.2024.
From August 12 to August 24 – "Yuzhnaya" boiler house, stage 2
From 9:00 on 12.08.2024 to 23:59 on 24.08.2024, repair of the heating main from the "Yuzhnaya" boiler house (Stage II) will be carried out. In connection with this, there will be no hot water supply to the following facilities:
- Moskovsky Ave., 7; 7 building 2; 8; 8a; 9a; 9b; 9 building 1, 9 building 2; 10; 11 building 1, 11 building 2, 11 building 3, 11 building 4, 11 building 5; 12; 13 building 1, 13 building 2, 13 building 3, 13 building 4, 13 building 5, 13 building 6 (Kindergarten No. 78); 14; 15; 15a; 16; 17/1; 18; 19 building 1, 19 building 2; 19/2 building 1; 20; 20a; 20b; 21a; 21 building 2, 21 building 3, 21 building 4; 22; 22a (Bathhouse); 23; 24; 25; 26; 26 building 1; 27; 27 building 1, 27 building 2; 28; 28a (Secondary School No. 11); 29 building 2; 30; 31; 31a; 32; 32a; 33 (University); 34; 35; 35a (Kindergarten No. 96); 36; 36 building 1; 37; 38; 39; 39 building 1, 39 building 3; 40; 41; 41a (Gymnasium No. 9); 42; 43; 43a (Polyclinic); 43 building 1; 44; 45; 45a (Secondary School No. 38); 45b; 45 building 1, 45 building 2; 46; 47; 47 building 1, 47 building 2; 48; 49; 49a; 50; 51a; 51; 52; 53; 54; 55; 56; 57; 57b; 59; 59a; 59b; 58; 60 ("Evroopt"); 62; 62 building 1; 64; 64a; 66; 86 ("Santa" store);
- Smolenskaya St., 4, building 1; 4 building 2; 4 building 3; 4 building 4; 4 building 5, 4 building 6;
- Stroiteley Ave., 4; 6; 8 building 1; 8 building 3; 10; 12; 12 building 1; 16, 18a (Kindergarten No. 85); 18 building 1, 18 building 2, 18 building 3, 18 building 4; 20 building 1, 20 building 2, 20 building 3; 22 building 1, 22 building 2, 22 building 3, 22 building 4, 22 building 5, 22 building 6, 22 building 7; 24 building 1, 24 building 2, 24 building 3, 24 building 4, 24 building 5, 24 building 5a; 26/13;
- P. Brovki St., 1a (Kindergarten No. 93); 1 building 1; 3a; 3 building 1, 3 building 2; 5a; 5b (Kindergarten No. 2); 5 building 1; 7 building 1, 7 building 2, 7 building 3, 7 building 4 (Secondary School No. 12), 7 building 5; 9 building 1, 9 building 2, 9 building 3; 11a (Kindergarten No. 88); 11 building 1, 11 building 2, 11 building 3; 13a; 15 building 5, 16a; 16; 17; 17a; 19; 18; 20a; 20; 21; 22; 23; 23a (Secondary School No. 42); 32; 32a; all facilities of OJSC "Vityaz";
- Pobedy Ave., 1; 2; 3; 3a (Kindergarten No. 52); 3b; 3g; 3 building 1; 3 building 2; 3 building 3; 4a (Kindergarten No. 95); 4; 5; 5 building 1; 5 building 2; 6; 6 building 1, 6 building 2; 7; 7 building 1; 7 building 2; 8; 8a; 10; 12;
- Chkalov St., 1; 1/17; 2; 3; 4 Bldg. 2; 5; 6; 7; 7 Bldg.1; 7 Bldg. 2, 8; 10; 11/14 (Kindergarten No. 84); 12; 14; 14 Bldg. 1; 14 Bldg. 2; 9 Bldg. 1, 9 Bldg. 2, 9 Bldg. 3, 9 Bldg. 4, 9 Bldg. 5, 9 Bldg. 6, 9 Bldg. 7, 9 Bldg. 8, 9 Bldg. 9; 11a; 11 Bldg. 1, 11 Bldg. 1a, 11 Bldg. 2, 11 Bldg. 3, 11 Bldg. 3a (Kindergarten No. 16), 11 Bldg. 4, 11 Bldg. 7, 11 Bldg. 8, 11 Bldg. 9; 13; 14a (Kindergarten No. 18); 14v (children's polyclinic); 15; 16; 16 Bldg. 2; 17; 17 Bldg.1; 17/2; 18; 18 Bldg. 1; 18 Bldg. 2; 18 Bldg.3; 18a ("Vesta" 139); 19a (Gymnasium No. 5); 19 Bldg. 1, 19 Bldg. 2, 19 Bldg. 3, 19 Bldg. 4; 22 (Secondary School No. 25); 24a (bowling alley); 24 Bldg. 1; 24 Bldg. 2; 24 Bldg. 3; 24 Bldg. 4; 24 Bldg. 5; 24 Bldg. 6; 24 Bldg. 7.
- Starobabinovichsky Tract, 2; 4;
- 2nd Prodolnaya St., 3;
- Lenina St., 1/8; 1a; 3; 3a; 3b; 5a; 5/1; 11v; 15/9;
- Ofitserskaya St., 2;
- Chernyakhovsky Ave., 1; 3; 4; 5; 6; 6 Bldg. 1, 6 Bldg. 2, 6 Bldg. 3, 6 Bldg. 4, 6 Bldg. 5, 6 Bldg. 6; 7; 8; 8a; 10; 12; 18a (Kindergarten No. 6); 20 Bldg. 4; 20 Bldg. 5; 20 Bldg. 6; 20 Bldg. 7; 22 Bldg.2; 22 Bldg. 3; 22 Bldg. 4; 22 Bldg.5; 22 Bldg. 6; 22 Bldg. 7; 24; 24d; 24 Bldg. 2; 26; 26 Bldg. 1; 26 Bldg. 2; 26 Bldg. 3; 26 Bldg. 4; 26 Bldg. 5;
- Zhestkova St., 7; 8/1; 10a; 11; 11a; 12; 13; 14; 14a; 15; 16; 16a; 17; 18; 18a, 19; 20; 21; 21a; 22; 23; 24; 25;
- Shrader St., 1; 3; 3 Bldg. 1; 6; 7; 8; 10; 12; 14;
- Shubina St., 2; 3; 4; 5/13;
- Khmelnitsky St., 9; 9a; 11/6; 12; 20; 24; 27a; 29 (Kindergarten No. 36); 30; 31;
- 3rd Kollektivnaya St., 6.
During the period from 9:00 AM on 12.08.2024 to 11:59 PM on 13.08.2024, hydraulic testing of heating networks at elevated pressure will be carried out.
From August 19 to August 31 – "Severnaya" boiler house
From 9:00 AM on 19.08.2024 to 11:59 PM on 31.08.2024, planned repairs of heating networks from the "Severnaya" boiler house will be carried out. In connection with this, hot water supply will be unavailable at the following facilities:
in the area of Gagarin, Keramzitovaya, Serov, Skorina, Babushkina, Osipenko, 7th Surazhskaya streets, 3rd Sadovaya, 24, 26, 30, 2nd Sadovaya, 2, 4th Sadovaya, 1st and 2nd Polyarnaya, 1st Sovkhozny Lane, Lyudnikov Avenue, 2 (SSH No. 3), 4, 10.
From 9:00 on 20.08.2024 to 23:59 on 21.08.2024, hydraulic tests of heating networks at increased pressure will be carried out.
Owners of heat supply systems must carry out major repairs of heating networks, heating units, and internal heating systems, including flushing and pressure testing of pipelines.
Heat supply systems that have not undergone major repairs and preparation of equipment for the 2024-2025 heating period will not be allowed.
During the heating network testing days, pipeline damage may occur, which can lead to significant leaks of network water. During this time, please remove all valuables from basement premises.
If damage to the heating networks is detected, please report it immediately by phone: 67-04-41, 67-04-14, 67-06-47.